To jumpstart
long-delayed generation plans Cabinet approved multiple power plants this week
to be quick-tracked for completion including two 300 MW coal power plants,
while also dusting off two 300 MW LNG power plants and considering renewables
worth as much as $100 million.
No power plants
have built-in Sri Lanka in the last five years. In 2014 the Norochcholai power
plant's second and third phases were completed, adding 570 MW to the national
grid. A 60 MW plant installed in the following year but since then power plants
listed in the Sri Lankan Public Utilities Commission's (PUCSL) Long Term
Generation Plan were limited to paper.
Over the past
four years, repeated Cabinet approvals have struggled to see any implementation
on the ground with a lot of confusion and cancellations. This week, Cabinet
re-examined some of the previously listed plants, including the 300 MW LNG
plant to be constructed in Kerawalapitiya as a joint venture with the Ceylon
Electricity Board (CEB) with Indian funding.
Following
high-level discussions between Sri Lanka and India, this plant was initially
granted Cabinet approval in September 2018 as a 500 MW joint project with
Indian company NTPC. According to a statement from the press issued at the weekly
Cabinet briefing, Power and Energy Minister Mahinda Amaraweera's proposal also
included the development of a coal-fired power plant. The plant in question
involves a capacity of 600 MW as an extension to the existing Norochcholai
power plant.
Another sizeable
coal-fired power plant, however, will be in contravention of the President's
Office's announcement this month that Sri Lanka would seek 80 per cent of
renewable energy by 2030. Environmental severe issues about coal-fired power
plants have also raised, and Sri Lanka is now among the countries most impacted
by climate change, experts said.
"In
Kerawalapitiya, acceleration of construction activities of a second LNG plant
with a capacity of 300 MW proposed with funding from the Asian Development
Bank," the Cabinet paper stated.
In addition to
two LNG power plants and the massive coal power plant, the Government is also
looking to accelerate the development of already under development hydropower
plants and regeneration power projects. The focus will also give on the swift
implementation of solar energy projects that can fund under an Indian
Government grant of $100 million.
Cabinet also
gave the approval to contract installation of new equipment in thermal power
plants for a separate Cabinet report. The expansion of the Kelanitissa 132 kV
Gas Insulated Switchgear (GIS) thus commenced. The objective was to connect the
132 Busbar in the Kelanitissa grid substation with proposed gas turbines. The
Cabinet of Ministers, therefore, approved the proposal submitted by the
Minister of Power and Energy to grant the contract for the procurement,
installation and supervision of two 145 kV Double Busbar (GIS) and the contract
for the administration, evaluation and measurement of 145 kV Double Busbar
(GIS) to the original supplier, Asea Brown Boveri Lanka Ltd.
OSL Take: With
LNG exploration becoming a possible business prospect in the country, investors
who become pioneers in capitalising on this stand to enjoy huge benefits. The
Cabinet of Ministers, therefore, approved the proposal submitted by the
Minister of Power and Energy to grant the contract for the procurement,
installation and supervision of two 145 kV Double Busbar (GIS) and the contract
for the administration, evaluation and measurement of 145 kV Double Busbar
(GIS) to the original supplier, Asea Brown Boveri Lanka Ltd.
No comments:
Post a Comment